The full exterior of 1200 will be painted the month of September 2022. This will affect entry to the condos. Doors and windows will be taped off.
What to expect:
Paint prep usually consists of: power washing 2 days, let building dry for one week. Scrape, remove downspouts/screens, tape off windows and doors, and then paint within sections.
Whole process should only take 3 weeks for the 1200 building. So if the painters start on Sept 6 after labor day, the work should be done around the 30th (give or take with weather).
If you have any questions, please contact Mike Gooch, Maintenance Manager