The 1200 Roofing Replacement will be complete by June 8th. Then the chimney chases rebuild will begin, and may take up to 4 weeks. After the chimney chase project is complete, the painters will paint the chimney chases. ETA for completion is still on target for August. … [Read more...]
900 Captain Jack Painting Update 6.30.2022 – ETA completion July 15
Attn owners in the 900 bldg: The painting vendor is now working on the back side of the building. Estimated completion date is around July 15. … [Read more...]
800 Solitaire Building Skylights will be replaced June 3rd.
The new skylights were on back order for Solitaire and have arrived. The roofing company will install the new skylights on Friday, June 3rd. … [Read more...]
1400 Clearwater Building Chimney Chase Project begins June 6th
The roofing tear off and replacement is almost complete. The Chimney Chase rebuild will begin Monday, June 6th. … [Read more...]
1200 Trapper Building Roofing & Chimney Chase project begins June 13
The roofing tear off will begin at the 1200 Trapper Building on June 13. Time share condo apartments will be kept vacant during the roofing tear off process. … [Read more...]
900 Captain Jack Building Painting Update 5.25.2022
5-25-22 Update: The painting crew has completed the power washing on the 900 Bldg. The building will need dry out for a week or so and then the painters will return to prep for painting. This may be around the first of June. Please be aware that during the prepping and paint process there will be limited access to the windows and doors. This usually takes a week for the front entry side and … [Read more...]
1400 Clearwater Roofing Progress Update 5.25.2022
Attached is a photo showing the progress of roofing at the 1400 BLDG as of May 25th. The roofers started on the deck side over 1402 and have torn off up to unit 1410. … [Read more...]
Current Forest Road Closures & Trailhead Accessibility
Mt. Baker-Snoqualmie NF Road and Trail Conditions For more information, please visit: https://usfs.maps.arcgis.com/apps/MapSeries/index.html?appid=2f5351d70b0d4ed9b13d372e9d109fcb Road Name: SR-542 Mt. Baker Hwy – ARTIST POINT ACCESS Road Number SR-542 Mt. Baker Hwy Condition Closed Beyond Heather Meadows Notes Updated 05/06/2022. The Mt. Baker Highway is closed … [Read more...]
Annual Maintenance Week May 13 – May 20, Common Buildings CLOSED May 16 & 17
Snowater's Annual Maintenance week begins May 13 - May 20th. Many vendors will be on site to provide carpet cleaning, interior and exterior window cleaning, interior and exterior dryer vent cleaning, propane fireplace annual maintenance and cleaning, and more. Owners of full share condominium apartments were provided the opportunity to request these services. The Clubhouse, Recreation Building … [Read more...]
Friday, May 13 Snowater Office Hours 10 am – 5 pm
Friday, May 13, Snowater office hours 10 am - 5 pm. Maintenance Week begins Friday, May 13th. We will close at 5 pm this one day only. Regular Friday office hours will return on Friday, May 20th (10 am - 10 pm) … [Read more...]
- « Previous Page
- 1
- 2
- 3
- 4
- …
- 8
- Next Page »