Memorandum Date: Thursday March 23, 2023 To: All Building Chairs and Secretaries From: Nic Roggeman Subject: Snowater Capital Reserves With all the buzz swirling in the media about the safety of our banking system, we wanted to assure you that Snowater’s Capital Reserves are safe. For the past 9 years, our capital reserves have been safely invested through our investment counsellor … [Read more...]
New Clubhouse Artwork
Photos supplied by Snowater owners, Nic Roggeman and Mark Alway. … [Read more...]
ELOSS UPDATE- PHASE 1, DAY 1
The excavation is under way! Iverson mobilized their equipment and broke ground September 6th. The new septic dosing tank is scheduled to arrive next Thursday the 15th. With all heavy machinery, there is lots of noise and vehicles coming from the parking area in front of buildings 300/400. Typical work day will be 7:30-5pm M-F. … [Read more...]
1200 Trapper Building Update – Chimney Chase & Painting
1200 Building Update Owners of the 1200 bldg: Here is the latest update on your building. The chimney chase work was completed on Monday, August 22 Crew came back on Wednesday to remove all plywood protective sheets from upper back decks and lower back bay windows Chimney chase caps are on order and will be installed when completed Painting crew will be power washing the … [Read more...]
1100 Equinox Roofing Project Update
1100 Equinox Building Update The roofing crew is almost done with your building, estimated completion date is August 31. The siding crew will be starting on the chimney chases in the next couple of days. Owner of Topside hopes to have the building completed by mid-September. Siding work occurs Monday - Friday, 8 am - 5 pm. During the siding work, it is OK for owners and guests to occupy … [Read more...]
1200 Trapper Exterior Building Painting Start Date September 6th, 2022
The full exterior of 1200 will be painted the month of September 2022. This will affect entry to the condos. Doors and windows will be taped off. What to expect: Paint prep usually consists of: power washing 2 days, let building dry for one week. Scrape, remove downspouts/screens, tape off windows and doors, and then paint within sections. Whole process should only take 3 weeks for the … [Read more...]
1200 Trapper Chimney Chase update 7/27/2022
The siding crew began construction at the 1200 Chimney Chases July 27th, 2022. The estimated time frame for completion is Labor Day weekend; September 2, 2022. Exterior building painting estimated start date will be September 6th. … [Read more...]
Power outage affects Clubhouse, condo buildings and Glacier Water District
A buried power line near the Clubhouse failed early morning August 9th which caused power failure at the Clubhouse, several condo buildings and affected the Glacier Water District. It was repaired early afternoon. … [Read more...]
Roofing tear-off begins at 1100 Equinox Building
The Equinox 1100 Building will be unavailable for occupancy until September 2nd at the earliest. … [Read more...]
1400 Roofing update 6.30.22
The chimney chase project is scheduled for completion by July 8th. The chimney caps are custom ordered and may be slightly delayed in arriving. The painters will be painting the chimney chases in July. The work at the 1400 building will be completed on schedule in July. … [Read more...]